            Oxygen free jumping Acton

  TRAMPOLINE & LEIsure Park REFURBISHMENT

September 2022

The Brief

Oakwhite had developed and fitted out Acton trampoline park in 2015 after 8 years of use the park needed refreshing and modernaising.

The programme was 8 weeks and needed to be completed for the spring holiday.  We were to install 2 new kitchens, new café counter, refurbish party rooms and café area. Creat a quite zone for parents to sit in, install a viewing mezzanine over the park. Decorate throughout including the spraying of the park area.

New attractions were added to the park area. Clip and climb, kiddies play area and a great big air bag.

 

The Stripout

The Kitchen on the middle floor was stripped out including the walls, to extend the café area. The showers and changing rooms on the 2nd floor were removed including the walls to make way for a new kitchen. The entrance was reconfigured with the removal of the briefing room and the entrance counter.

The Fitout

Create a new kitchen on the 2nd floor and 1st floor. Install a new café counter and fridge display. Decorate the whole park including spraying the ceiling and walls to the trampoline area. Install new mezzanine on the 1st floor to extend the café seating and viewing area. Install new windows into the park from the party rooms. Up grade electrics and mechanical as required. Instal new furniture.  Some of the trampolines were dismantled and clip and climb installed along with a giant air bag.

Testimonial

Steve and Ian are delighted with the works carried out and pleased that it had been finished on time and within budget.